Slatted shed build timeline and concrete curing rules
A typical 3-bay to 4-bay slatted shed takes 10 to 16 weeks on site, built around a non-negotiable 28-day concrete curing period after wall pours before gang slats are craned on or stone is backfilled.
Week-by-week sequence from digger arrival to livestock housing, and why rushing crane slat placement before 28 days cracks slurry tanks.
Free, no obligation. One local builder prices it, not five.
- 10–16 wkstypical on-site build window
- 7 daysminimum damp curing protection
- 28 daysfull cure before slat loading
- C30/37–C35/45DAFM S.100 EN 206 concrete grades

Week-by-week slatted shed construction schedule
Working backwards from November cattle housing means concrete tank walls should be poured no later than August or early September. Cold, wet autumn weather slows cement hydration and stretches excavation time on heavy soils.
Phase 1: Excavation & stone bed
- Typical window
- Weeks 1 to 2
- What happens in the yard
- Dig tank pit, break any rock, lay land drain/sump around footing and compact clean blinding stone.
Phase 2: Tank base, rebar & walls
- Typical window
- Weeks 2 to 4
- What happens in the yard
- Tie double rebar mat, pour base with waterbar kicker, erect steel wall shuttering and pour S.100 concrete.
Phase 3: Moisture & structural curing
- Typical window
- Weeks 5 to 8 (28 days)
- What happens in the yard
- Protect fresh walls from drying for 7 days; let concrete reach full 28-day design strength before heavy loads.
Phase 4: Crane slats & backfill
- Typical window
- Weeks 8 to 9
- What happens in the yard
- Lift IS EN 12737 gang slats onto 150 mm wall bearings, then backfill clean drainage stone evenly outside walls.
Phase 5: Steel frame, roof & penning
- Typical window
- Weeks 10 to 14
- What happens in the yard
- Bolt portal steel stanchions, sheet roof with non-drip liner, pour feed passage/lie-back and hang barriers.
Work out your slatted shed cost
Four quick taps and our bay-by-bay price shows before we ask for a phone number. One local farm shed builder rings you, not five.
4 bays suckler slatted shed, TAMS 3 still to decide: €96,000 to €130,800 ex VAT.
How the bay-by-bay figure is worked out
The guide multiplies going Irish per-bay slatted build ranges (excavation, shuttered reinforced tank, gang slats, external agitation point, steel frame, cladding and penning) by bay count, ex VAT. When you select 40% or 60% TAMS 3, the indicative net figure deducts grant aid up to a single €90,000 investment ceiling; splitting slurry storage under the separate 60% Nutrient Storage ceiling or building as a registered farm partnership (€160,000 ceiling) increases grant support further. Rock breaking, high water tables, rubber slat mats and extra feed passage widths are priced when the builder walks the yard.
Why concrete curing decides whether a slurry tank lasts 40 years
- DAFM S.100 certified ready-mix only. Use Mix B (C30/37) or Mix A (C35/45) from an EN 206 certified quarry with cube-test records and retain every docket.
- Protect against wind and sun for 7 days. Cover walls with polythene or apply curing membrane immediately after stripping shutters so shrinkage micro-cracks never open.
- Wait the full 28 days before backfilling or craning slats. Concrete hits ~75% strength at 7 days, but 16 ft 6 in gang slats and heavy excavator backfilling push full design shear onto green walls.
- Never backfill one wall before slats brace the top. Unsupported tank walls can bow inward if wet clay or heavy stone is pushed tight against them before top slat propping is in place.
More slatted shed guides
Slatted tanks and extensionsPer-m³ tank rates, agitation bays and tying into existing yards.
Cattle slats and rubber mats12 ft 6 in, 14 ft 6 in and 16 ft 6 in gang slats, axle loads and mat costs.
TAMS 3 40% and 60% grantsSeparate €90,000 Nutrient Storage ceiling, 70% importation and approval rules.
VAT 58 reclaim for farmersFlat-rate VAT refunds via ROS eRepayments within 4 years.
Agitation & slurry gas safetyDAFM S.123 external points, 6 m spacing and ridge ventilation.
Slatted shed prices by bayEvery bay rate, tank m³ rate, rubber mat and DAFM reference cost.Common slatted shed questions
When should I start building to house cattle by November?
Aim to start excavation by June or July at the latest so tank curing finishes in warm weather and steel erection plus yard concrete cure cleanly before winter stock arrive.
Can steel stanchions be erected while the tank is curing?
External perimeter pad foundations away from the tank pit can be poured and cured alongside the tank, though heavy crane outriggers should stay well back from newly poured tank walls until 28 days pass.
What happens if heavy rain fills the excavated tank pit?
Builders install a perimeter land drain and temporary submersible sump pump outside the footing stone so water never washes cement fines out of fresh base concrete.
How long do I wait before driving a tractor on a newly poured feed passage?
Allow at least 7 to 14 days for light yard movement and a full 28 days before heavy laden diet feeders or 3,000-gallon slurry tankers drive on fresh 150 mm concrete slabs.
All slatted shed pages and technical guides
Slatted shed types
Specs, tanks & grants

See your bay-by-bay cost before a builder rings
Pick the slatted shed layout, bay count, TAMS 3 rate and county. When you want a site quote, your outline goes to a single farm shed builder in your county.